By Jason Given - November 2026 - 11 min read
If your builder goes broke in the middle of your build, your home loan does not disappear and neither does the money you have not drawn yet. You still owe what has been paid out so far, and the rest of the loan sits there until a new builder is ready to finish the job. Building Indemnity Insurance then helps with the extra cost of finishing, up to a limit.
That is the short version. The detail matters, because the insurance does not cover everything, and the new builder will almost always cost more than what was left on the old contract. This guide covers what to do first, how the insurance works in SA, what happens to your construction loan, and how to plan for the gap.
This is general information, not legal advice. For your rights under the contract, talk to a lawyer or Consumer and Business Services (CBS).
Builder gone bust? The first things to do
- ✓1. Confirm what has happened. Under the insurance, a company builder is insolvent when "an administrator or liquidator has been appointed to the company", and an individual builder is insolvent when they become bankrupt (SAFA). You can search the company on ASIC's registers. Rumours and a quiet site are not the same as insolvency.
- ✓2. Stop paying the builder. Do not pay any invoice ahead of work done. Payments made in advance of a stage may not be recoverable if the builder is insolvent (SAFA).
- ✓3. Find your insurance certificate. The builder had to give it to you before work started (SA Government). It names the insurer and the work insured.
- ✓4. Contact the insurer. If you think you have grounds for a claim, contact your insurer. SAFA lists QBE on 1300 790 723 and Assetinsure on (02) 9251 8055 (SAFA).
- ✓5. Secure the site. If the home is not at lock-up, you may need to secure it. The insurer will normally cover reasonable costs, but talk to your claims officer first (SAFA).
- ✓6. Tell your lender and your broker. The lender needs to know before any further progress payment is asked for, and it will tell you what it needs to keep the loan on track.
- ✓7. Get advice before you end the contract. Ending a building contract can have consequences. Talk to a lawyer, or call CBS on 131 882 (CBS).
Keep a record of everything: who you spoke to, when, and copies of every email and invoice. The insurer will want the contract, the payment history and photos of the site.
SA Building Indemnity Insurance: when it pays
Building Indemnity Insurance is required under the Building Work Contractors Act 1995 for domestic building work that needs council approval and costs $20,000 or more (SAFA). Before 10 November 2025 the threshold was $12,000. The builder takes it out and pays for it, and an owner builder cannot take it out for their own work (SA Government).
It is "last resort" insurance. It only responds if the builder dies, disappears or becomes insolvent (SAFA). When it does, it covers two things:
- ✓Finishing the work. It "contributes to the additional costs of completing a building project above the original contract price" (SAFA).
- ✓Defects. The cost of fixing defects for up to 5 years from completion (SAFA).
The policy limit depends on when the policy was issued
| Insurer | Policy issued | Limit |
|---|---|---|
| QBE | 1 July 2017 to 30 September 2025 | $150,000 |
| QBE | From 1 October 2025 | $250,000 |
| Assetinsure | 24 May 2023 to 9 November 2025 | $150,000 |
| Assetinsure | From 10 November 2025 | $250,000 |
Source: SAFA. Older QBE policies (1 July 2013 to 30 June 2017) have an $80,000 limit. The limit is the total for all claims on the project, unfinished work and defects together.
The limit rose because claims have been large. CBS said in July 2025 that the government had provided a record $18.7 million in the previous financial year to help people finish their homes, and that the Qattro Built collapse in September 2023 had led to 251 claims (CBS).
What it does not cover
- ✗Delays on their own, or a dispute between you and the builder (SAFA). Those go to CBS, not the insurer.
- ✗Loan interest, rent and legal fees. SAFA lists loan interest, rent-related losses, legal fees, building report fees and an excess of up to $400 as not covered (SAFA).
- ✗Money paid ahead of the work. CBS warns that extra or staged payments "aren't covered by insurance" (CBS).
- ✗Deposits paid before the insurance existed. Deposits are covered once the builder has taken out the insurance. Before that, they are at your risk (SAFA).
What happens to your construction loan
A construction loan is paid out in stages, so when a builder collapses your loan is split in two:
- ✓The drawn part. Everything paid to the builder so far, including the land if it is in the same loan. You owe this and you keep making the repayments, usually interest only during the build.
- ✓The undrawn part. The money set aside for the stages not yet done. It has not been paid to anyone, so it is not lost. The lender will not release it until a new builder is in place.
Before the lender releases any more money, expect it to ask for the new building contract, the new builder's details and insurance, and an updated valuation or inspection of the part-built home. It will want to see that the undrawn loan, plus any insurance payout and your own money, is enough to finish the home.
The time limit on your construction loan
Construction loans are approved for a build period, and the loan contract usually sets a date by which the home should be finished. A collapse can push you past it. Ask your lender early about an extension, before the date passes rather than after. Our guide to how construction loans work in SA covers the build period and the switch to full repayments.
Interest keeps running
While the site sits idle you still pay interest on the drawn amount, and if you are renting you are paying rent as well. Neither is covered by the insurance. Work out how many months of both you could carry, because finding a new builder and agreeing a new contract takes time.
A dollar example: the gap between the old contract and the new one
Here is how the numbers can look when a builder fails after the frame stage. These are example figures only.
| Item | Amount |
|---|---|
| Original building contract | $450,000 |
| Paid to the builder so far (deposit and stages to frame) | $270,000 |
| Left on the original contract, still undrawn in your loan | $180,000 |
| New builder's price to finish the home | $250,000 |
| Extra cost above the original contract price | $70,000 |
Illustrative only. The insurer decides what it pays, after its own assessment and the excess. Not a quote or an offer of credit.
In this example, the $180,000 left in the loan goes towards the new builder, and the insurance may contribute towards the extra $70,000 above the original price, up to the policy limit. The interest on the $270,000 already drawn, any rent and any legal costs during the delay are yours. If the insurer's contribution falls short, the rest comes from your savings or extra borrowing.
If you need more money to finish
There are a few ways to cover a shortfall. Each depends on your situation and the lender:
- ✓Your own savings, or money from family.
- ✓A larger loan from your lender. This is a new application. The lender will look at your income and expenses again, and at what the finished home will be worth. A home loan top up explains how lenders assess an increase.
- ✓Equity in another property, if you own one.
- ✓A different lender. Refinancing a part-built home is harder, because fewer lenders will take one on, but it is not impossible.
- ✓Hardship help. If you cannot keep up repayments while the site is stalled, ask your lender about financial hardship before you miss one.
Finding a replacement builder
The insurer will usually want quotes from licensed builders to complete the work before it assesses your claim (SAFA). When you choose one:
- ✓Check the licence. Search the builder's licence online or call CBS on 131 882 (CBS).
- ✓Ask about insurance for the new contract. Confirm the new builder will take out Building Indemnity Insurance where it is required, and give you the certificate before starting.
- ✓Get a fixed price for what is left. Part-built homes carry unknowns. Ask the builder to list any work it will not take responsibility for, such as defects in the existing frame.
- ✓Keep the lender in the loop. Send the new contract to your lender and broker before you sign, so the finance and the contract line up.
Before you sign: how to lower the risk
You cannot rule out a builder failing, but you can limit the damage if it happens:
- ✓Check the builder. Check the licence, ask to see recent homes and talk to past clients.
- ✓Keep the deposit to 5%. For a contract of $20,000 or more, the deposit should be no more than 5% of the total (SA Government).
- ✓Check the insurance yourself. CBS has found forged certificates, so verify yours at bii.sa.gov.au (CBS).
- ✓Never pay ahead of the stage. In SA a builder can only ask for "a genuine progress payment" for work already done (Law Handbook SA).
- ✓Use the cooling off period. You have 5 clear business days after signing a domestic building contract to end it by written notice (Law Handbook SA).
- ✓Leave room in the budget. A contingency and a few months of spare cash flow give you time if the build stops. Our guide to the cost to build a house in Adelaide covers what to allow for.
If you are buying off the plan or in a new estate, read our guide to sunset clauses in SA as well. For a dispute that is not an insolvency, the SA Government sets out the options on its page about disputes with a builder.
How we can help
We cannot give legal advice or handle your insurance claim. What we can do is talk to your lender with you, work out how much of the loan is drawn and undrawn, and look at how to fund any gap, whether that is an increase with your current lender or another lender on our panel of 60+. No fee from us - the lender pays us. If you are still choosing a builder, see how construction loans in Adelaide work with us.
Frequently asked questions
Do I still have to pay my mortgage if my builder goes broke?
Yes. You owe the amount already drawn and need to keep making the repayments. The undrawn part of the loan is not lost. The lender holds it until a new builder is ready to finish the home. If you cannot keep up, ask your lender about hardship before you miss a payment.
How much does building indemnity insurance pay in SA?
For policies issued from 10 November 2025, the limit is $250,000, and QBE policies have had that limit since 1 October 2025. Older policies have lower limits of $150,000 or $80,000. The limit is the total for all claims on the project, unfinished work and defects together.
Does building indemnity insurance cover my deposit?
SAFA says deposits are covered once the builder has taken out the insurance. Before the insurance is in place, deposits are at your risk. Payments made ahead of the work are not covered.
Can I claim if my builder is just running late?
No. The insurance only responds if the builder dies, disappears or becomes insolvent. Delays on their own and disputes with the builder are not covered. Contact CBS for help with a dispute.
What happens to the money left in my construction loan?
It stays in the loan. The lender will usually release it to the new builder once it has the new contract, checked the part-built home and is satisfied the money available will finish it.
Will my lender lend me more to finish the build?
It may. A bigger loan is a new application, so the lender looks again at your income, expenses and the value of the finished home. If your lender will not help, another lender may, although fewer lenders take on part-built homes.
SA Government: building indemnity insurance - when it is required, the certificate, owner builders, page updated 19 February 2026
SAFA: building indemnity insurance for homeowners - when it pays, $250,000 limit, exclusions, insurer contacts
SAFA: about building indemnity insurance - limits by insurer and date, cover above the original contract price, $20,000 threshold
SAFA: building indemnity insurance FAQs - insolvency, deposits, securing the site, what is not covered
CBS: building and renovating tips to stay protected - forged certificates, staged payments, checking a licence
CBS media release: greater protection for home builders - claims and payouts, 11 July 2025
CBS: contact - phone 131 882
SA Government: builder responsibilities - deposit no more than 5% for contracts of $20,000 or more, updated 10 November 2025
Law Handbook SA: domestic building work contracts - progress payments and the 5 clear business day cooling off period
SA Government: disputes with a builder or tradesperson - options for disputes
ASIC: search ASIC's registers - company status
Builder in trouble? Talk to us before the next payment
Tell us where your build is up to. Jason or Steve will work out what is drawn, what is left and how to fund the finish with your lender.